Oman's $475M Mazoon Copper Project Targets First Output in Q1 2027
Oman Mining Development Company will start up its six-pit copper mine in early 2027, shipping concentrate while a domestic smelter stays uneconomic.
Oman Mining Development Company plans to begin production at its Mazoon Copper Project in the first quarter of 2027. The development costs $475 million, or OMR 183 million.
The project spans 20 square kilometres and consists of six open-pit mines, with capacity to process 2.5 million tonnes of ore a year. Reserves are estimated at 29 million tonnes of copper ore, enough for an operating life of about 10 years. The target is 115,000 tonnes of copper concentrate annually.
Chief executive Matar bin Salem Al Badi said output will initially be exported as concentrate. Current volumes are not enough to justify a domestic smelter, he said. Higher production in future could support one, and a smelter would let Oman process more of its mineral resources locally and increase their value.
China's Hongda International is responsible for mining operations and services at the site, according to Al Badi. At the concentration plant, copper content is raised from roughly 1% in the ore to 21.5%. The ore also carries economically viable gold at 0.5 to 0.8 grams per tonne, and the company is studying recovery methods to extract more value from the deposit.
Exploration at Mazoon is aimed at expanding reserves and extending production.
The company holds 14 mining concession areas across Oman and plans nearly $1 billion in investments, alongside existing assets valued at $857 million, or OMR 330 million. Construction of Shuwaimiyah Port, one of its upcoming projects, is expected to begin in 2027. It is also developing mineral processing and manufacturing projects intended to expand downstream industries.
Copper demand is expected to rise on electrification, artificial intelligence infrastructure and industrial expansion. The International Energy Agency projects growth of 7 million tonnes by 2040 under its Stated Policies Scenario, led by electricity networks, electric vehicles, data centres, construction and industry, and warns of a possible 25% supply shortfall by 2035. Declining ore grades, rising development costs and fewer new discoveries are holding back production growth.
For Oman, the smelter question turns on scale. Concentrate exports generate revenue without one, but the refining margin stays abroad. Whether the country moves downstream depends on pushing output past the threshold Al Badi described.