Orascom Breaks Ground on Jordan's $6.7 Billion Desalination Project

Orascom Construction has started construction on the Aqaba-Amman Water Desalination and Conveyance Project in Jordan, an infrastructure investment valued at more than $6.7 billion that is intended to cover roughly 40% of the country's drinking water needs.

The development centers on a seawater desalination plant on the Gulf of Aqaba with capacity of 851,000 cubic meters per day. A 418-kilometer pipeline will carry treated water north to Amman. Building the system is scheduled to take four years, with deliveries expected to begin by the end of 2030, Water and Irrigation Minister Raed Abu Al-Soud said. Once running, the network is designed to provide about 300 million cubic meters of potable water a year, easing demand on the kingdom's scarce freshwater supplies.

Prince Faisal bin Al Hussein attended the Aqaba groundbreaking on Wednesday on behalf of King Abdullah II. Jordanian officials and representatives of the international consortium were also present.

On Thursday, Jordan signed a $6.6 billion agreement with Meridiam, the lead developer, to begin implementation work during the Jordan-EU Investment Conference.

Construction and financing

Orascom Construction is working with French water group SUEZ in an engineering, procurement and construction joint venture for the desalination plant. The contractor is also part of a separate EPC joint venture handling the transmission network.

Meridiam and SUEZ are developing the scheme under a 30-year public-private partnership concession. After construction, Orascom and SUEZ will operate and maintain the desalination and conveyance facilities for 26 years. The wider consortium includes VINCI Construction Grands Projets and the Jordan Social Security Investment Fund, Meridiam said.

A 280-megawatt solar photovoltaic plant will supply about 30% of the project's electricity, SUEZ said. The Green Climate Fund has committed $295 million in concessional loans and grants, its largest financing commitment to a single country.

Water security

Jordan ranks among the world's most water-scarce countries. Annual renewable freshwater availability is below 100 cubic meters per person, SUEZ said. The national water carrier is expected to raise per capita availability from about 60 cubic meters a year to 110 cubic meters and increase household deliveries from one to three days a week.

Meridiam estimates the project will generate more than 33,000 jobs during construction and another 2,600 during operations. It is also expected to cut carbon emissions by at least 6.7 million metric tons over the concession period.

Orascom's regional reach

The Jordan award extends Orascom Construction's water infrastructure business across Egypt, North Africa and the Gulf. The company says projects in those markets have combined capacity exceeding 17 million cubic meters per day.

"We are proud to play a key role in this landmark project, which will provide sustainable supply of drinking water to Jordan," Osama Bishai, Orascom Construction's chief executive, said in a company statement.

Orascom Construction placed third in a 2026 ranking of the region's 10 largest construction companies, a list led by Bishai. It also ranked 16th in a 2026 ranking of Egypt's 50 most valuable companies. Nassef Sawiris, a major Orascom shareholder, placed fourth in a 2026 ranking of the world's richest Arabs, with an estimated net worth of $9.6 billion as of November 19, 2026.

Highlight any sentence and Anec will explain it.
TB
Tariq Benali
Tariq Benali covers business and corporate news across the UAE and MENA for Anecdoted, tracking the deals, leadership moves and regulatory shifts behind the region's companies.

Read next

CEER signs $693m financing with Arab National Bank and Riyad BankCleanTechCEER signs $693m financing with Arab National Bank and Riyad BankGCC Waste Management Market Projected to Surpass $104 Billion by 2031CleanTechGCC Waste Management Market Projected to Surpass $104 Billion by 2031GCC Waste Market Set to Reach $104B by 2031 as Construction Debris DominatesCleanTechGCC Waste Market Set to Reach $104B by 2031 as Construction Debris Dominates
Daily · Free

The Morning Wire

The funding wire, one story worth your time, and what's moving across MENA.